第九章测试
1.The disagreement resulted from one party of a transaction totally or partially unable to perform the obligation and liability stipulated in the contract is ( ).
A:settlement of disputes B:breach of contract C:dispute D:claim
答案:C
2.The seller may breach the sales due to the followings EXCEPT ( ).
A:the goods which do not meet the standards stipulated in the contract B:the insufficient documents relating to goods C:failing to make payment D:failing to deliver the goods 3.A force majeure event should have the following features EXCEPT that ( )
A:neither the buyer nor the seller can control the situation B:it is not due to the negligence of the buyer or seller C:either the buyer or the seller can control the situation D:it happens after the contract is signed 4.If the sales contract between a Chinese company and a Japanese company stipulated that the arbitration shall be conducted in defendant's country. Which place may carry on arbitration if the Japanese company is the compliant?
A:Beijing B:Tokyo C:London D:New York 5.

When (  ) happens, the party that fails to perform the contract is allowed to relieve liabilities of the non-performance.


A:

pilferage of goods

B:

hurricane

C:

floods

D:

civil war

7.When a force majeure event takes place, the party concerned has no choice but to terminate the contract.
A:对 B:错 8.The arbitration award is final and binding on both parties.
A:错 B:对 9.Force majeure clause is a clause that mainly protects the right of the buyer.
A:对 B:错 10.In international trade, the claim only occurs between the seller and the buyer.
A:对 B:错