创新项目的要素
1.项目摘要的提炼原则PKU指的是什么?
A:Problem, Keywords, Units B:Process, Keywords, Urgent C:Project, Keywords, Uniqueness D:Plan, Keywords, Users
答案:C
2.挑选项目团队成员有哪些可行原则?
A:C+团队,按照所需资源找人组队 B:B+团队,挑选认同项目的目标 C:D+团队,挑选最听话的人来组队 D:A+团队,挑选能力最强的人组队
答案:AB
3.SMART目标指的是什么?
A:Specific,Measurable, Attainable, Reasonable, Time-based B:Smart,Measurable, Advanced, Relevant, Time-based C:Smart,Measurable, Attainable, Reasonable, Time-based D:Specific,Measurable, Attainable, Relevant, Time-based
答案:D
4.SMART目标设定中关键的因素是什么?
A:可考核 B:有明确时间限制 C:可量化 D:范围广、调整余度大
答案:ABC
5.SWOT态势分析法的SWOT分别指的是什么?
A:Stress, Weightiness, Operation, Timing B:Strengths, Weaknesses, Opportunities, Threats C:Status, World, Object, Treatment D:Strategy, Work, Open, Target
答案:B