1. Cause-and-effect diagram can demonstrate the number of defects by source.             ( )

  2. 答案:错
  3. Crashing often leads to rework and increased risk. ( )

  4. 答案:错
  5. Curve method can predict the trend of cost overrun and schedule delay based on the current status of cost and schedule variance. ( )

  6. 答案:对
  7. Risk transfer can reduce the probability of the occurrence of risk events.                 ( )

  8. 答案:错
  9. The actual progress can be compared with the planned schedule on the chart. The simple and intuitive method is Bar Chart. ( )

  10. 答案:对
  11. Quality audit can be performed only by internal auditors. ( )

  12. 答案:错
  13. Which of the following items are the advantages of projectized organization structure?( )

  14. 答案:Project team members work directly for the project manager###Communication becomes simple and easy###Project manager is fully responsible for the project
  15. The methods for creating WBS include ( )

  16. 答案:Top-down/bottom-up approach###Brainstorming
  17. EVM should be used continuously throughout the project to detect the variances while they are small and possibly easy to correct. ( )

  18. 答案:对
  19. The task is the highest level of the WBS. ( )

  20. 答案:错
  21. Proper scope planning is critical to project success. ( )

  22. 答案:错
  23. Which of the following are the process of project risk control? ( )
  24. The processes of project scope management include ( )
  25. Which of the following rules should quality control obey? ( )
  26. Since a project is temporary, its deliverables can not exist beyond the end of the project. ( )
  27. Which of the following are the basic principles of project cost control?( )
  28. Large projects are usually managed by ( )
  29. Which of the following are economic corrective measures of project cost control?( )
  30. The calculation of the total cost of a project from decision-making to execution and operation is called( )
  31. Which of the following statements is false? ( )
  32. Project resources consist of ( )
  33. Which of the following factors influence the project quality?( )
  34. Risk management is normally performed by ( )
  35. If the delayed time of one activity exceeds its Total Float in a network schedule, then ( )
  36. The scope change control board approves a significant scope change. The first document that the project manager should updated would be ( )
  37. A risk response strategy that reduces the probability or impact of the event without altering the project’s objectives is called( )
  38. If an activity on the critical path takes longer than anticipated, then ( )
  39. In which organizational structure would the project manager possess the greatest amount of authority?( )
  40. In which life-cycle phase would the financial risk of a project be the greatest?( )
  41. In an network schedule, if Activity P needs 3 days to be completed, but 2 days aparting from the latest finish time, then ( )
  42. Which of the following participants can define project quality according to today’s view of quality management ( )
  43. What traditional project management emphasizes is ( )
  44. What are the components of Juran’s Trilogy?( )
  45. The most accurate project estimating is ( )
  46. Which of the following items is not the elements of activity?( )
  47. Activities with no time duration are called ( )
  48. If CV=-20000 Yuan in March and CV=-30000 Yuan in April, in order to determine whether or not the situation has really deteriorated because of an unfavorable cost variance, we would need to calculate ( )
  49. The major disadvantage of using bar charts to manage a project is that bar charts ( )
  50. As processes improve over the long run, ( ) will go down as the need to inspect in quality decreases.
  51. The performance measurement baseline is most often composed of three baselines ( )
  52. Which of the following items demonstrates the logic relationship that Activity B cannot start earlier than the completion of Activity A?( )
  53. Most people believe that the best way to train someone in project management is through ( )
  54. The source of many project estimating risks is ( )
  55. Project stakeholders have various expectations and needs for the project, mainly because ( )
  56. The desired outcomes or results of a project are called ( )
  57. Risk mitigation and risk transfer are examples of(  )
  58. Which of the following are the process of project risk management (  )
  59. Risk analysis is the second process of project risk management. (  )
  60. Risk factors commonly exist in project design phase, which may lead to reduced economic benefits and even project failure. (  )
  61. In which life-cycle phase would project uncertainty be the greatest (  )
  62. Which of the following items on project quality management is false? (  )
  63. What is the percentage range of of cumulative frequency for major quality factors (i.e. A factors) in Pareto analysis should be (  )
  64. Which of the following items are the features of TQM?(  )
  65. Project manager has the ultimate responsibility for quality management on the project.(  )
  66. ISO 9000 standards are the series of standards that outline the requirements for quality management system developed by PMI.(  )
  67. The evaluation index of variance analysis in EVM include (  )
  68. The abbreviation of actually expended amount in completing the work accomplished within a given time period is BCWP.(  )
  69. Bottom-up estimating is the definitive estimate, which is made without any detailed engineering data.  (  )
  70. If BCWP=1200, BCWS=1000, and ACWP=1300, the project is (   )
  71. The common types of project estimating exclude (   )
  72. Which of the following network scheduling technique is mostly used in schedule software systems today.(  )
  73. Which of the following are the common techniques for schedule compression (  )
  74. Crashing and outsourcing are two main techniques can be used for duration compression.  (  )
  75. Critical Path Method (CPM) is suitable for complex but fairly routine project with minimal uncertainty in the project completion time. (  )
  76. Which of the following principles is the most basic methodology of project time management. (  )
  77. Project scope can influence the time, quality and cost of the project. (  )
  78. Work Package is in the managerial level of the WBS.(  )
  79. Project initiation is approved for the following main reasons (  )
  80. Commonly, Work Breakdown Structure can be constructed as (  )
  81. The document that officially sanctions the project is the (  )
  82. In which type of matrix structure would a project manager most likely have a command of technology (  )
  83. In which organization structure would the project manager is fully responsible for the project (  )
  84. Project team member probably may lose his or her job in matrix organizational form if the project gets cancelled. (  )
  85. Which of the following items are the roles of a project manager (  )
  86. Generally, project manager is the soul of project team. (  )
  87. The main objectives of project management are (  )
  88. The person responsible for balance the time, cost and quality objectives to achieve project success is (  )
  89. The knowledge areas in PMBOK include: (  )
  90. There are five process groups in PMBOK.(  )
  91. The temporary nature of projects means that a project has a short duration.  (  )