第五章单元测试
The common types of project estimating exclude ( )
If BCWP=1200, BCWS=1000, and ACWP=1300, the project is ( )
The evaluation index of variance analysis in EVM include ( )
Bottom-up estimating is the definitive estimate, which is made without any detailed engineering data. ( )
The abbreviation of actually expended amount in completing the work accomplished within a given time period is BCWP.( )
A:Analogous estimating B:Parametric estimating C:Bottom-up estimating D:Quick-and-dirty estimating
答案:Quick-and-dirty estimating
A:Behind schedule and under budget B:Behind schedule and over budget C:Ahead of schedule and over budget D:Ahead of schedule and under budget
A:Project performance index (PPI) B:Schedule variance (SV) C:Cost performance index (CPI) D:Cost variance (CV)
A:错 B:对
A:对 B:错