第五章单元测试
  1. The common types of project estimating exclude (   )


  2. A:Analogous estimating  B:Parametric estimating C:Bottom-up estimating D:Quick-and-dirty estimating
    答案:Quick-and-dirty estimating
  3. If BCWP=1200, BCWS=1000, and ACWP=1300, the project is (   )


  4. A:Behind schedule and under budget B:Behind schedule and over budget C:Ahead of schedule and over budget D:Ahead of schedule and under budget
  5. The evaluation index of variance analysis in EVM include (  )


  6. A:Project performance index (PPI) B:Schedule variance (SV) C:Cost performance index (CPI) D:Cost variance (CV)
  7. Bottom-up estimating is the definitive estimate, which is made without any detailed engineering data.  (  )


  8. A:错 B:对
  9. The abbreviation of actually expended amount in completing the work accomplished within a given time period is BCWP.(  )


  10. A:对 B:错